Scoring extensions and avoiding penalties

27.11.07

 

Failure to give written notice of delay properly may expose a party to liquidated damages for late completion. The first instance decision in Steria Limited v Sigma Wireless Communications Limited provides useful guidance on whether giving written notice can ever be a condition precedent to an entitlement to an extension of time, and the form such a notice should take.

The judgment also addresses the issue of whether a liquidated damages clause amounts to a penalty or not. This case goes a step further than that of Multiplex Construction v Honeywell Control Systems [2007]. In this case the entitlement to liquidated damages was directly linked to the condition precedent.

Wragge & Co acted for Steria.

Read our analysis to find out more about the judgment.

For an update on the steps you can take, see our action points.

Key Contact

Sian Llewellyn, partner, +44 (0)121 629 1846, sian_llewellyn@wragge.com

This alert may contain information of general interest about current legal issues, but does not give legal advice.